We have been assisting with the manufacture of some large bore pressurised hot water pipework to allow the connection of a temporary boiler situated in a hospital carpark.  We have fabricated and off site pressure tested all the pipework and penetrated the flow and return pipework to the existing energy centre (in the back ground). 

The glass fibre Kiosk was made and mounted on a galvanised steel frame which incorporated new flow and return headers with double valve and drain connections, expansions bellows,  along with presure guage connections,  flushing valves and dosing points.  The complete module was transported  and lifted into position in the carpark using a Hiab truck.

The temporary boiler whilst being temporarily connected with 6″ flexibles will shortly probably  be connected with steel pipework and lagged for the duration of the works.